Grant County PUD commissioners will delay a decision on starting condemnation proceedings along the proposed route of a new power line from Wanapum Dam to Quincy.
April 11, 2025
Stories this photo appears in:
April 14, 2025 2:50 a.m.
Decision delayed on condemnation proceedings along proposed power line route
EPHRATA — Grant County Public Utility District commissioners will delay a decision on beginning condemnation proceedings for property along the route of a projected power line between Wanapum Dam and Quincy for six weeks. Commissioners voted to table a resolution that would’ve started the condemnation proceedings at the April 8 meeting, following testimony from residents along the proposed route.