MATTAWA — Drivers heading south of Mattawa can expect State Route 243 to be closed for a short stretch between Mattawa and Desert Aire, beginning Monday.  

The city of Mattawa is working on upgrades to its sewer system, and Mattawa Public Works Director Juan Ledezma said the project would require upgrades to the connection between Portage Avenue and the city’s wastewater treatment facility. That requires removing and replacing pipes running under SR 243. 

“A contractor for the city will close the highway to cut the asphalt, excavate, and install a section of larger pipe,” according to a press release from the Washington Department of Transportation. “During that time, the highway will be closed and traffic will be routed through a signed local detour. Detour routes include rural county roads, and travelers should plan for reduced speeds through the area.” 

The work could take up to two weeks to complete, the press release said. 

It being mid-October, most projects are wrapping up for the winter. Paving is underway on a section of Schoonover Road north of Ritzville.  

Eight miles of Schoonover are being rebuilt; paving is projected to be completed by Oct. 21, said Adams County Engineer Scott Yaeger. Once the paving is completed, crews will be striping the road and installing guard rails. The last day of the project is scheduled for Oct. 29. 

“It looks good out there,” Yaeger said. 

Crews are about to wrap up the second year of work on the Vantage Bridge, with construction continuing until the end of the month, weather permitting. 

“Crews plan to reopen access across the bridge to all lanes of traffic by the end of October,” according to a WASHDOT press release.