PUBLIC NOTICE
|
July 6, 2016 1:00 PM
WORK TO BE PERFORMED BY DISTRICT PERSONNEL
WORK TO BE PERFORMED BY DISTRICT PERSONNEL
Public Utility District No. 2 of Grant County, Washington
with an estimated project cost over $25,000
Related to RCW 39.04.020
Description of Work: Grant PUD will be replacing approximately 55 existing power poles along Co. Rd. 39 NE from N.5 to Co Rd R NE as part of our concrete pole replacement project. This work is necessary to bring the existing overhead power line to current specifications and to replace the existing concrete poles on the electrical system for a standard wood pole.
Estimated Cost of Project: $120,000.00
Date Work is to Commence: July 18, 2016
District Representative: Jaime Esparza
#07025/5203149
Pub.: July 6, 2016