Thursday, May 02, 2024
29.0°F

PUBLIC NOTICE

| October 9, 2014 1:00 PM

WORK TO BE PERFORMED BY DISTRICT PERSONNEL

WORK TO BE PERFORMED BY DISTRICT PERSONNEL

Public Utility District No. 2 of Grant County, Washington

with an estimated project cost over $25,000

Related to RCW 39.04.020

Description of Work: The District will be building two new transmission structures and replacing three existing transmission structures to extend the Larson-Stratford 115kV transmission line to the new Avista Stratford Switchyard.

Estimated Cost of Project: $125,000.00

Date of Work is to Commence: 11/3/14

District Representative: Russ Seiler

#10034/4036682

Pub: October 9, 2014