PUBLIC NOTICE

| January 31, 2014 12:00 PM

WORK TO BE PERFORMED BY DISTRICT PERSONNEL

WORK TO BE PERFORMED BY DISTRICT PERSONNEL

Public Utility District No. 2 of Grant County, Washington

with an estimated project cost over $25,000

Related to RCW 39.04.020

Description of Work: PUD crews will be replacing poles and adding capacitor banks along Highway 28 Frontage Road east of 12th Avenue SW and along B Street SW also east of 12th Avenue SW.

This project will reduce impacts on the substation and transmission line as well as increase reliability in the area.

Estimated Cost of Project: $50,000.00. Cost includes all overhead/allocations.

Work is to Commence: Mid February 2014.

District Representative: Alan Balciar

#01065/3566004