WORK TO BE PERFORMED BY DISTRICT PERSONNEL

WORK TO BE PERFORMED BY DISTRICT PERSONNEL

Public Utility District No. 2 of Grant County, Washington with an estimated project cost over $25,000 Related to RCW 39.04.020

Description of Work: The District will be replacing nine transmission structures in Moses Lake on the 115kV line between the Sand Dunes Substation and the Larson Substation. The project will begin near the intersection of Rd K SE and Rd 1 SE and end near the intersection of S Rees St and Filmore Dr.

Estimated Cost of Project: $140,000.00

Date Work is to Commence: 02/04/14

District Representative: Russ Seiler

#01060/3555345

Pub.: January 24, 2014