Friday, May 03, 2024
36.0°F

PUBLIC NOTICE INFORMATION

| February 18, 2011 12:00 PM

WORK PERFORMED BY Grant County Public Utility District Personnel

estimated project cost over $25,000 related to RCW 39.04.020

WORK PERFORMED BY

Grant County Public Utility District Personnel

estimated project cost over $25,000

related to RCW 39.04.020

Work Description: District crews will be removing and installing three circuit breakers during a scheduled substation outage. In addition, two temporary overhead lines will be installed to bypass a future construction area associated with construction of an additional lineup at the substation, which is currently planned for the spring and summer months of this year.

Estimated Cost of Work:     $60,000.00

Work Scheduled to Start:     2/23/2011

#02058/1486505

Pub.: February 18, 2011