PUBLIC NOTICE INFORMATION
|
February 18, 2011 12:00 PM
WORK PERFORMED BY Grant County Public Utility District Personnel
estimated project cost over $25,000 related to RCW 39.04.020
WORK PERFORMED BY
Grant County Public Utility District Personnel
estimated project cost over $25,000
related to RCW 39.04.020
Work Description: District crews will be removing and installing three circuit breakers during a scheduled substation outage. In addition, two temporary overhead lines will be installed to bypass a future construction area associated with construction of an additional lineup at the substation, which is currently planned for the spring and summer months of this year.
Estimated Cost of Work: $60,000.00
Work Scheduled to Start: 2/23/2011
#02058/1486505
Pub.: February 18, 2011