NOTICE OF ROAD CONSTRUCTION

| August 1, 2011 8:21 AM

North Central Construction, Inc. will begin road construction of

Dry Coulee Rd. Said construction will begin on 08/01/2011 and end

approximately 09/16/2011. This road project includes the

reconstruction of 3.91 miles of county road and includes roadway

excavation

North Central Construction, Inc. will begin road construction of Dry Coulee Rd. Said construction will begin on 08/01/2011 and end approximately 09/16/2011. This road project includes the reconstruction of 3.91 miles of county road and includes roadway excavation, embankment compaction, crushed surfacing base course, maintenance rock, drainage items, seeding, fertilizing, mulching and other work all in accordance with the plans and specifications. Any questions or concerns can be directed to North Central Construction's main office at (509) 765-5885.

#08025/1811225

Pub.: July 29, August 1 & 2, 2011