Sealed bids will be received at City Hall, 321 South Balsam,

(P.O. Box 1579), Moses Lake, Washington 98837 until May 17, 2011,

11:00 A.M., for the above-named improvement. Said bids will be

opened and publicly read at that time. All bids shall be received

before said opening time in sealed envelopes with “STORMWATER

DECANT FACILITY – 2011” marked plainly thereon.

STORMWATER DECANT FACILITY – 2011

Moses Lake, Washington

Sealed bids will be received at City Hall, 321 South Balsam, (P.O. Box 1579), Moses Lake, Washington 98837 until May 17, 2011, 11:00 A.M., for the above-named improvement. Said bids will be opened and publicly read at that time. All bids shall be received before said opening time in sealed envelopes with “STORMWATER DECANT FACILITY – 2011” marked plainly thereon.

All bids shall be accompanied by a deposit in the form of a postal money order, cashier’s check, or bond in an amount equal to 5 percent of the maximum total amount of the bid. Should the successful bidder fail to enter into a contract or furnish a satisfactory contract bond within the time stated in the specifications, the deposit shall be forfeited to the City.

Plans and specifications shall be obtained at the City Hall at the above address for a non-refundable fee of $30.00. Only bids from bidders who have purchased plans and specifications at the City Hall will be accepted. Copies of plans and specifications are on file for review at various construction councils.

Contact person: Richard A. Law, P.E. 509-764-3782

PROJECT DESCRIPTION:

This project consists of constructing a 180 foot by 60 foot reinforced concrete slab with 180 feet of trench drain connected to a series of catch basins, coalescing plate oil/water separator and connected to an existing manhole. The project also consists of constructing 300 feet of new perimeter fencing and relocating 800 feet of existing perimeter fencing, 20,000 square feet of asphalt surfacing surrounding the concrete pad, yard hydrants and water pipe from an existing water connection, installing 15 trees, irrigation system, seeding 750 square yards of lawn, and grading and graveling approximately 1.25 acres. Contractor will also provide and install precast ecology block walls totaling 380 lineal feet by 2 blocks high.

Estimated Project Cost: $295,000.00

The City Council reserves the right to reject any or all bids if such action is in the best interest of the City.