Othello to repair well
Othello City Council designated well 5 to be in a state of emergency to forgo the bidding process to repair it immediately.
Shaft failed
OTHELLO — Othello City Council designated well 5 to be in a state of emergency to forgo the bidding process to repair it immediately.
The well was taken offline due to a shaft failure, according to a city document.
The city declared a state of emergency because well 6 is also offline being rehabilitated and because water demand spikes during the summertime.
When well 5 was functioning, it produced 1,500 gallons of water per minute.
Council opted to fix the problem with the installation of a vertical turbine capable of producing 1,400 gallons of water per minute, according to a city document. It has a 400 horsepower motor.
The cost with tax is $246,450.
Councilmember Ken Caylor voted to approve the contract with Schneider Equipment and Councilmember Mark Snyder seconded. The vote was unanimous.
Work to repair the well will begin immediately.
— Staff report