On Sunday the crews finished compacting backfill after the canal had been fixed. The canal is fully operational again as of Sunday.
August 12, 2024
Stories this photo appears in:
August 13, 2024 1 a.m.
Canal breach fixed in record-breaking time
MOSES LAKE — A breach in the East Low Canal was fixed within five days and back to delivering water by Saturday. Last Monday, there was a canal breach on the East Low Canal near Roads N and 4 Northeast. The East Columbia Basin Irrigation District began the dewatering process, removing water from the canal, immediately, said Jennifer Korfiatis, the public relations specialist at the East Columbia Basin Irrigation District, which maintains the canal.